What testing is required for building curtain walls?
Author:
Building curtain walls require physical performance testing (wind pressure resistance, air permeability, rainwater leakage, and plane deformation performance testing reports), which is generally referred to as the four properties testing of curtain walls, compatibility and adhesion testing reports of silicone structural adhesives and weather resistant sealants, and on-site tensile force testing reports of embedded parts.
1、 Building curtain wall:
It refers to the non load-bearing outer wall enclosure of a building, usually composed of panels (glass, metal plates, stone plates, ceramic plates, etc.) and supporting structures behind them. Building curtain walls refer to the non load-bearing outer wall enclosure of a building, usually composed of panels (glass, metal plates, stone plates, ceramic plates, etc.) and supporting structures behind them (aluminum beam columns, steel structures, glass ribs, etc.). Composed of aluminum beams and columns, steel structures, glass ribs, etc.
The performance testing method for building curtain walls is:
(1) The acceptance of curtain wall engineering should be carried out after the completion of the building (excluding secondary decoration), and its surface should be wiped clean before acceptance.
(2) The following documents should be submitted during the acceptance of curtain wall engineering:
① Design drawings, documents, design modifications, and material substitution documents;
② Material and component factory quality certificates, profile test reports, structural silicone sealant compatibility and adhesion test reports;
③ Acceptance documents for concealed works;
④ Construction and installation self inspection records.
(3) The quality of curtain wall engineering should be inspected according to visual inspection and sampling inspection. Using one curtain wall as the inspection unit, each curtain wall should be inspected.
(4) The visual inspection of curtain wall engineering should be carried out according to the following eight requirements:
① The frame material of the exposed frame curtain wall should be vertical and horizontal; The joint of curtain wall partition glass should be straight and horizontal, with uniform joint width and in accordance with design requirements;
② The variety, specifications, and color of glass should be consistent with the design, and the color should be basically uniform. Aluminum alloy materials should not have phenomena such as alkali precipitation, mold, or coating detachment;
③ The installation direction of the glass should be correct;
④ The color of metal materials should match the design, and the color should be basically uniform. Aluminum alloy materials should not have delamination.
⑤ Aluminum alloy decorative pressure plate should have a flat surface and no visible deformation, fatigue lines, or local crushing defects;
⑥ The sealing, settlement joint, expansion joint, seismic joint treatment, and lightning protection system of the upper and lower sides and sides of the curtain wall should comply with the specifications.
⑦ The covering and decoration of concealed nodes in the curtain wall should be neat and aesthetically pleasing.
⑧ The curtain wall shall not leak.
Latest News
2023-09-07
How is witness sampling conducted?
Witness sampling is one of the supervisory management methods. Witness refers to the activity of on-site supervision by the supervising engineer on the completion of a certain process by the contracting unit. Witness sampling refers to the supervision activity of on-site sampling of materials, semi-finished products, and components related to structural safety used in engineering projects, as well as the inspection of the effectiveness of process activities.
2023-09-07
What are the main testing items for building environment testing
Environmental testing mainly detects factors such as chemical pollutants and physical and biological pollution. Environmental detection and governance is a highly technical emerging industry that utilizes GIS technology to design environmental detection networks. The information collected from environmental detection can be stored and displayed in a timely manner through GIS, and detailed site monitoring and analysis can be conducted on the selected evaluation area.
2023-09-07
How to detect the quality of construction projects?
Construction project quality inspection refers to the inspection of construction materials, building components, equipment, and physical quality of the construction site, as well as the testing of structural safety and main usage functions of the construction project design, in accordance with relevant national laws, regulations, and standards, commissioned by the inspection agency in the activities of building construction, expansion, renovation, and municipal infrastructure engineering.
2023-09-07
What testing is required for building curtain walls?
Building curtain walls require physical performance testing (wind pressure resistance, air permeability, rainwater leakage, and plane deformation performance testing reports), which is generally referred to as the four properties testing of curtain walls, compatibility and adhesion testing reports of silicone structural adhesives and weather resistant sealants, and on-site tensile force testing reports of embedded parts.
2023-09-07
What tests are required for curtain walls
Before installation, conduct a comprehensive inspection of the building and promptly rectify or rework any non-conforming areas.